Will the first progress payment repay borrowing for a signed change order?

Commercial general contractors financing

A general contractor collecting $310,000 a month signs a $60,000 change order for extra steel on a school renovation. The supplier needs $26,000 and the installer needs $12,000 before the first payment arrives. The contractor has $8,000 available after covering the original scope. The signed order allows billing after inspection and pays nothing at signing.

Financing options at a glance

If the customer will certify more completed work on the first bill, how much would cover the draw? With the same 10% holdback, $30,000 divided by 0.90 requires at least $33,333.34 in approved billing before fees. Confirm the inspection date, billing cutoff and actual collection date with the project manager. If the completed work cannot support that bill, negotiate supplier timing or arrange repayment from a later documented collection.

Relief Capital is an independent business financing consultancy. A financing advisor can help you compare fees and repayment schedules for your business.

Illustrative cash gap

$38,000 due before the next expected cash arrives, less $8,000 in available cash, leaves a gap of $30,000.

Hypothetical example. Actual financing costs and eligibility depend on the business and provider.

What to check first

The contractor needs $30,000 before inspection. Assume the first approved progress bill is $32,000 and the agreement holds back 10% of that bill until closeout. The first collection is $28,800. Applying it all to the draw still leaves $1,200 of principal plus financing charges. The $60,000 contract price alone tells the owner little about that first payoff.